Schedule for Expanded depot at Högdalen
Construction
/
/
Planning process
-
-
Preporatory work
Preparatory work begins, for example pipe laying and preparation of business establishment areas.
-
Permit application
The permit application is submitted to the Land and Environment Court. The Land and Environment Court will primarily consider the drainage of groundwater. Noise, vibrations and emissions will also be regulated in the court’s examination.
-
Review of the railway plan
The finished proposals for the lines and stations are put on display for inspection together with the environmental impact analysis. The views and comments received during previous consultations and how they have been dealt with are also reported.
-
-
-
Environmental Ruling
Court decision. The Land and Environment Court primarily considers the drainage of groundwater. Noise, vibrations and emissions to water will also be regulated in the court’s examination.
-
The railway plan is approved
The railway plan is approved by the Transport Administration. If no appeal is lodged, it becomes legally binding.
-
Construction start
The work of building the new Metro will be noticeable. We are planning thoroughly, so that everyday life will continue as normal throughout the construction period.
-