{"id":46561,"date":"2026-10-12T09:16:15","date_gmt":"2026-10-12T07:16:15","guid":{"rendered":"https:\/\/nyatunnelbanan.se\/?p=46561"},"modified":"2026-10-12T09:17:58","modified_gmt":"2026-10-12T07:17:58","slug":"updated-cost-and-schedule-estimate","status":"publish","type":"post","link":"https:\/\/nyatunnelbanan.se\/en\/news\/updated-cost-and-schedule-estimate\/","title":{"rendered":"Updated cost and schedule estimate"},"content":{"rendered":"\n<p class=\"wp-block-paragraph\">During 2026, the administration has carried out a comprehensive review of costs, schedules, and remaining work across all projects within the metro expansion. A new final cost estimate for the entire expansion has now been presented. The new estimate incorporates cost increases, risks, and index adjustments in a more systematic and comprehensive way than before.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The new estimate indicates increased costs and revised schedules for the various projects. <\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><a href=\"https:\/\/nyatunnelbanan.se\/en\/news\/review-complete-updated-estimate-for-stockholms-new-metro-expansion\/\" data-type=\"link\" data-id=\"https:\/\/nyatunnelbanan.se\/en\/news\/review-complete-updated-estimate-for-stockholms-new-metro-expansion\/\">You can read more about the results of the review here<\/a><\/p>\n\n\n\n<p class=\"wp-block-paragraph\">At the end of September, the new estimate was presented to the Regional Transport Committee of Region Stockholm and the funding parties, who are now analyzing the results.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">\u2013 Ongoing procurements will continue, but the the result of the new estimate will in some cases lead to adjustments in the schedules. At present, we cannot say whether the new estimate will have any other consequences for ongoing or planned procurements. We expect to be able to provide updated information during November, says Iveta Sandstr\u00f6m, Head of Procurement at the New Metro Administration.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"> <a href=\"https:\/\/nyatunnelbanan.se\/en\/current-procurements\/\" data-type=\"page\" data-id=\"4274\">The procurement schedule shows the current planning<\/a><\/p>\n\n\n\n<h2 class=\"wp-block-heading\">The work continues<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">The construction of the new metro continues across all projects, with a strong focus on progress, quality, and delivering the infrastructure that the region needs.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Region Stockholm\u2019s Administration for Extended Metro has presented an updated cost and schedule estimate for the entire metro expansion.<\/p>\n","protected":false},"author":3,"featured_media":46558,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"inline_featured_image":false,"footnotes":""},"categories":[161,149],"tags":[326,330],"class_list":["post-46561","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-procurement","category-upphandling-en","tag-top-procurement","tag-upphandling-i-topp-en"],"acf":[],"_links":{"self":[{"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/posts\/46561","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/users\/3"}],"replies":[{"embeddable":true,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/comments?post=46561"}],"version-history":[{"count":2,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/posts\/46561\/revisions"}],"predecessor-version":[{"id":46563,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/posts\/46561\/revisions\/46563"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/media\/46558"}],"wp:attachment":[{"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/media?parent=46561"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/categories?post=46561"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/nyatunnelbanan.se\/en\/wp-json\/wp\/v2\/tags?post=46561"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}