Q&A Supplier Day 2020
During the Suppliers day 2020 we received a lot of questions. Below you'll find the answers.
For the Sofia station, are there not dangers or hazardous to only have elevators? In case of fire, terrorist attack etc.
We have the requirement to have two separate ways of emergency exit. The first option are the elevators, the second will be regular stairs. The elevators and stairs are separate fire cells. As a third option it is possible to use the servicetunnel and acesstunnel in order to evacuate. In case of a loss of electricity there will be reserve power supply located in the servicetunnel.
How will be the emergency exit under a fire, explosion, when lifts or electricity will be off to work? For instance, in station Sofia, if there is cut of electricity, and not able to use lifts.
We have the requirement to have two separate ways of emergency exit. The first option are the elevators, the second will be regular stairs. The elevators and stairs are separate fire cells. As a third option it is possible to use the servicetunnel and acesstunnel in order to evacuate. In case of a loss of electricity there will be reserve power supply located in the servicetunnel.
What if you have a fire in the elevator?
There will be smokedetectors in the shaft and an elevator will go to a floor plan for evacuation. Beside the elevators there will also be two stairwells in the station for evacuation.
I understand fire can be managed, but what if there is an attack, as in London for example, will that not be dangerous?
We can not be specific about this question but different kind of scenarios has been taken into account when designing the station.
What is the deadline for Arenastaden Underground Package?
2020-01-28
Will you be sharing today's event presentation documents?
Yes they are published om our website - nyatunnelbanan.se. Here you will find all the presentations.
Perhaps you should explain what BEST means, for the benefit of international viewers.
BEST is a swedish abbrevation for Bana, El, Signal, Tele. Rail, Eletricity, Signal, Telecomunication in english.
Is it possible get a hard copy of the supplier day brochure?
Send us an e-mail on nyatunnelbanan@sll.se with your adress and how many copies you want an we will send them to you.
With regards to https://e.jublia.com/SupplierDay/, the companies' representatives do not publish their full contact details. Will you being sharing the full contact details?
No, the Jubila app will requier a consent from both parties to make contact.
Will some one be presenting 2021 projects? We wish to hear especially about FUT ID # 5713.
Planned procurment april 2021 to nov 2021. 2,7 km main tunnel with exibitions halls. More technical details is found in our "entreprenör broschyren".
FUT ID # 5713 is not described in detail. We just read the name of the project. What are the name of persons responsible for this package 5713? So that we can arrange meetings with them via JUBLIA.
Planned procurment april 2021 to nov 2021. 2,7 km main tunnel with exibitions halls. More technical details is found in our "entreprenör broschyren".
Can you please more talk about the FUT ID # 5713 that is planned to be launched in February 2021.
Planned procurment april 2021 to nov 2021. 2,7 km main tunnel with exibitions halls. More technical details is found in our "entreprenör broschyren".
Who is the companies that construct the metro?
Awarded contracts are presented on our website www.nyatunnelbanan.se
What is requirement for getting pre-qualified in TransQ? And where to learn more about the procedure?
All suppliers can contact Achilles for registration in the TransQ system. www.achilles.com
www.nyatunnelbanan.se/en/procurement-procedure
Where will tender documents (scope and specifications) be published? When will these be available?
To receive an invitation to our contract procurements, the supplier must be registered in TransQ. Selected suppliers will receive a link to the tender documents. Some of our other procurements are publiched in TendSign.
More information
How do companies access the Workforce Logiq platform?
If You register Your companie at www.workforecelogic.com You will get information about upcoming assignments.
More information.
Besides building new lines, how will potential capacity issues be adressed?
Our sister administration i Region Stockholm are continously working on this. They analyse the future capacity situation and possible measures. Such mesures can be related to signaling system and rolling stock.
Can you please more talk about the PINK LINE ( future project )
In Region Stokholm there is ongoing planning, design and production only for the metro project presented at the supplier day. No more metro projects are financed.
How important is it with fire proof materials in the tracks and tunnels?
It depends on many things, for example interval between the train and the train type so it's difficult to give a short correct answer.
What are the plans of handling the obvious obsolescence in signalling?
Decision to extend the existing system are taken in cooperation vith Trafikförvaltningen. Questions about signalling strategy after the lines for nya tunnelbanan has been opened for trafic should be raised to Trafikfövaltningen.
What is the electrical load on the 33kV system. Maximum peak and in general when traffic runs?
It depends on many things, for example interval between the train and the train type so it's difficult to give a short correct answer.
Will there be any fire requirements for equipment in fan rooms?
There will be a smokedetector the fan room. In the Nya Tunnelbanan there is require that the firealarm is cover the whole system.
Existing construction requirements are very detailed. For the new metro, would you be open to different/innovative design and construction solutions?
General question. But for some technical areas the answer is no and for some other the answers is yes.
Are the glazed screens and evacuation systems going to be specific on a brand for future manteinance and consistency
No.
The tender for the small rectifier station which is going to be issued next year. Will it include also the electrical equipment such as switchgear, rectifiers and SAS?
No, that tender will include ground, rock and housingworks. The electrical equipment for that station is included in the awarded contratc 2676 Rectifier stations and substations.
What tender package does include ventilation equipment?
FU Brand och tunnelventilation + FU VVS.
Where are the rectifier stations including the switchgear equipments, rectifier stations and scada included for the depot and barkarby project?
The rectifier station and substations for the Barkarby project is included in the awarded contract 2676 Rectifier stations and substations. The switchgear equipments and scada for Barkarby are included in ongoing ID 4721.
There are a lot of individual d&b contracts for installations. How are the designs coordinated across contracts?
It will be handle in productionplanning and cordinationmeeting. Cordination will be done in development of FU.
Where is the procurement for switchgear, transformers and scada for the rectifier and service stations for the extension of the blue line included (Kungsträdgårdan, Söderort and Nacka)?
The rectifier station and substations for the Nacka o Söderort project is included in the awarded contract 2676 Rectifier stations and substations. The switchgear equipments and scada for Nacka o Söderort are included in the comming procurement ID26726 Electricity, telecom and control.
It is important to find the right suppliers. How do you check all parts of the documentation presented by the suppliers? For example: experience capacity and professionalism in human resources.
When a procurement is being made, we can request various reports and evidence. Responses to the requirements specified in the qualification are reviewed and evaluated together with the requested evidence. During the agreement period, set requirements are followed up on an ongoing basis.
Is it up to the winning contractor to hire their own designer for the EST parts or will it be pre-designed? Which designers are involved now?
All EST contracts will be execution contracts so they will be projected. There are different projectors on the different development sections.
Key figures on volumes for Sickla?
Contract Sickla includes:
- 800 m track and service tunnel incl.
- The space for station Sickla, platform room comprising a distance of about 300 m as well as technical spaces, ticket hall, two entrances, a ventilation shaft and two escalator shafts.
- 322,000 m3 rock shaft underground.
- 10 000 m3 rock shaft above ground.
- 15,000 m3 soil shaft.
- 3200 m3 of concrete underground.
- 4000 m3 of concrete above ground.