Procurement timetable update
We are currently conducting a renewed analysis of our procurement strategy to ensure that the contract structure selected for rock and civil works for the new Yellow line is optimal for achieving our goals (time, cost, quality) as well as creating attractive contract opportunities.
A consequence of this work is that two of our procurements, Rock and civil works station Östbergahöjden (77114) and TBM and station Årstaberg (77142), are being postponed until early 2026.
Apartfrom these changes, operations are proceeding according to the original timeline.
The analysis is expected to be completed during December, and the outcome will be communicated to the market as soon as it is finalized.