Procurement information June 2026, TBM tunnels and Southern Stations (ongoing procurement)
Read more:
Supplier update spring 2026
Supplier day october 2025
Decisions and documents, including the Railway Plan (Järnvägsplan) showing permanent and temporary land requirements.
Article: The New Metro is developing its procurement processes
Overview
The new subway line between Fridhemsplan and Älvsjö will consist of 6 stations. The track tunnels will be bored using two tunnel boring machines (TBMs), which will start south of Älvsjö station and bore northward all the way to Fridhemsplan. When the tunnel boring machines reach a station, the station cavern must already be blasted/excavated, and the TBMs will be pulled through the station space before continuing northward. To facilitate planning and execution, the contract includes both tunnel boring with TBMs and rock excavation works for the four southern stations: Älvsjö, Östbergahöjden, Årstafältet, and Årstaberg.
About the Contract
The contract comprises:
TBM Tunnel Driving
-
Design, manufacturing, delivery, and assembly of the TBMs (tunnel boring machines)
-
Tunnel driving along the entire route
-
Segmental lining/tunnel lining with concrete segments, including the manufacturing and installation of segments along the entire route.
Station Caverns and Vertical Shafts
-
Årstaberg: Station cavern and vertical shaft
-
Årstafältet: Station cavern and vertical shaft
-
Östbergahöjden: Station cavern (the vertical shaft is procured under a separate contract)
-
Älvsjö: Station cavern and vertical shaft
Temporary Technical Safety Installations (STI)
-
Temporary safety systems during the construction period (radio communication systems for emergency services, mobile telephony, evacuation alarms, as well as positioning and access control systems).
Temporary Installations (TFI)
-
Temporary electricity, lighting, ventilation, water and wastewater systems, including treatment plants and fire water.
Key Facts
Schedule (Planned)
-
Contract start: March 2028
-
Completion: 22 Quarters after contract start
-
The procurement schedule is available in the administration’s procurement timetable.
Procurement Structure
-
General contract
Form of Contract
-
Design-build contract (ABT 06) with technical solutions for which the client is responsible.
Form of Remuneration
-
Fixed price with quantity adjustment (remeasurement) and indexation.
Security Assessment
-
The awarded contractor may be granted access to security-classified information during the contract period.
Evaluation Model
- The contract will be awarded to the tenderer that has submitted the most economically advantageous tender for the Client based on the best price-quality ratio (lowest evaluation sum).